Jennings Strouss Attorneys,
Deborah A. Swanstrom and
Andrea I. Sarmentero Garzón, author “
New Laws Promote Development of Small Hydropower Projects,” published in the December issue of the American Bar Association’s
Energy and Natural Resources Litigation Committee Newsletter
New Laws Promote Development of Small Hydropower Projects
Hydropower
supplies about seven percent of the U.S. electricity demand and is
currently the nation’s largest source of renewable carbon-free energy.
The operational flexibility that pumped storage hydropower projects
provide to the grid, by responding rapidly to supply and demand
imbalances and maintaining power system stability, is particularly
beneficial. Yet, reportedly only three percent of the dams in the United
States currently generate hydropower. Congress therefore decided to
change existing laws to promote more expeditious development of small
hydropower projects.
On August 9, 2013, President Obama signed
into law two new Acts passed by Congress: (i) the Hydropower Regulatory
Efficiency Act, PL 113-23 (August 9, 2013) 127 Stat 493 (“Hydropower
Efficiency Act”); and (ii) the Bureau of Reclamation Small Conduit
Hydropower Development and Rural Jobs Act, PL 113-24 (August 9, 2013)
127 Stat 498 (“Reclamation Act”). Both Acts streamline and expedite the
regulatory approval process to facilitate development of small
hydropower projects.
The Hydropower Efficiency Act
The
Hydropower Efficiency Act: (1) expands the Federal Energy Regulatory
Commission (“FERC” or “Commission”) exemptions for small hydropower
projects and conduits; (2) establishes a general exemption from Federal
Power Act (“FPA”) license requirements for certain hydropower projects
(3) allows the term of preliminary permits to extend beyond three years;
(4) directs FERC to investigate the feasibility of an expedited
two-year licensing process for certain hydropower projects; and (5)
directs the Secretary of the Department of Energy (“DOE”) to conduct
certain studies.
- 1. Expansion of Existing Exemptions
This
new law expands the small project exemption, provided in the Public
Utility Regulatory Policies Act and codified in 16 U.S.C. § 2705(d), by
increasing the capacity of projects eligible for this exemption from 5
megawatts (“MW”) to 10 MW. The new law also expands the existing conduit
exemption, provided in the FPA and codified in 16 U.S.C. § 823a, by
increasing the capacity of non-municipal projects eligible for this
exemption from 15 MW to 40 MW. Municipal hydropower projects keep their
prior 40 MW eligibility threshold for conduit exemptions. The new law
maintains the FPA definition of “conduit” as any tunnel, canal,
pipeline, aqueduct, flume, ditch or similar manmade water conveyance
that is operated for the distribution of water for agricultural,
municipal, or industrial consumption and not primarily for the
generation of electricity.
- 2. General Exemption from License Requirements
The
new law exempts from the FPA’s license requirements small hydropower
projects that meet the following criteria: (1) use for electric power
generation only the hydroelectric potential of a non-federally owned
conduit, (2) have a maximum installed capacity of 5 MW, and (3) are not
currently licensed or exempted from license requirements.
The
Hydropower Efficiency Act requires any person, state, or municipality
proposing to construct a qualifying conduit hydropower facility to file
with FERC a notice of intent. FERC recently posted a template of notice
of intent on its website.
The Act also requires FERC to make an
initial determination as to whether the facility meets the qualifying
criteria within fifteen days after receiving such a notice of intent. If
the initial determination finds that the hydropower project meets the
criteria for exemption, FERC must publish public notice of the notice of
intent. If an entity contests whether the hydropower project meets the
criteria for an exemption, FERC must issue a final determination within
forty-five days after the date of publication of the public notice. If
no entity contests whether the hydropower project meets the criteria for
an exemption, then the project will be deemed to meet the criteria for
waiver within forty-five days after the date of publication of the
public notice without further FERC action.
- 3. Extension of Preliminary Permits
FERC
is now authorized to extend the preliminary permit term for up to two
additional years beyond the three years currently allowed if FERC finds
that the permittee has implemented activities under the permit in good
faith and with reasonable diligence. In the prior regime, there was no
extension of time for expired preliminary permits. The permittee was and
still is allowed to file another preliminary permit application for the
same location but it is not guaranteed to keep its licensing priority
because the second preliminary permit application, like the initial
permit application, is open to potential competing applications by other
entities.
- 4. Expedited Licensing Process
Currently,
licensing processes for hydropower projects may take up to five years.
To expedite the licensing of low impact hydropower projects, the new law
directs FERC to investigate the feasibility of issuing a license for
hydropower projects at non-powered dams and closed loop pumped storage
projects in a two-year period. Significantly, the new law states that
this two-year period shall include any FERC pre-licensing process.
FERC
must hold a series of workshops to solicit public comment on how to
implement the expedited licensing process and develop the applicable
qualification criteria. On October 22, 2013, FERC held its first
workshop under Docket No. AD13-9-000. On January 2, 2014 FERC issued a
Notice opening a three-month window to file petitions for expedited
hydro license under a pilot program starting February 5, 2014 and ending
on May 5, 2014. The projects to be filed must comply with the following
minimum criteria:
- Must cause little to no change to existing surface and groundwater flows and uses;
- Must not adversely affect federally listed threatened and endangered species;
- If
the project is proposed to be located at or use a federal dam, the
request to use the two-year process must include a letter from the dam
owner saying the plan is feasible;
- If the project would use any
public park, recreation area, or wildlife refuge, the request to use the
two-year process must include a letter from the managing entity giving
its approval to use the site; and
- For a closed-loop pumped storage project, the project must not be continuously connected to a naturally flowing water feature.
FERC
will select the projects that best fit within these minimum criteria
and initiate the pilot program to test the feasibility of an expedited
two-year expedited licensing process. By February 2017, FERC must hold a
final workshop to solicit public comment on the effectiveness of the
tested two-year licensing process.
- 5. DOE Studies
The
Hydropower Efficiency Act directs DOE to study: (1) the technical
flexibility that existing pumped storage facilities can provide to
support intermittent renewable electric energy generation, including the
potential for such facilities to be upgraded or retrofitted with
advanced commercially available technology; and (2) the technical
potential of existing pumped storage facilities and new advanced pumped
storage facilities to provide grid reliability benefits.
The Reclamation Act
The
Reclamation Act: (1) provides that the Bureau of Reclamation
(“Reclamation”) Power Resources Office is the lead office of small
conduit hydropower processes; (2) defines “small conduit hydropower” as a
facility capable of producing 5 MW or less of electric capacity; (3)
excludes small conduit hydropower projects from requirements under the
National Environmental Policy Act of 1969 (“NEPA”); and (4) establishes a
right of first refusal for the lease of power privilege to irrigation
districts or water users associations.
- 1. Lead Office
The
new Reclamation Act amends the Reclamation Project Act of 1939 to
authorize the Secretary of the Interior (acting through Reclamation) to
contract for the development of small conduit hydropower projects.
Reclamation’s Power Resources Office is established as the lead office
of small conduit hydropower policy and procedure setting activities.
According to the Congressional Research Service’ summary of the enacted
bill, 113th Congress, 2013–2015. H.R. 678, (April 10, 2013) this “lead
office” role is intended to exclude such activities from FERC’s
jurisdiction.
- 2. NEPA Categorical Exclusion
The
new law requires the Bureau to apply its categorical exclusion process
under NEPA to qualifying small conduit hydropower projects. This
exclusion does not include the siting of associated transmission
facilities on federal lands. The application of this categorical
exclusion under NEPA means that these small conduit hydropower projects
in Reclamation’s conduits could be allowed to proceed without preparing
NEPA environmental documents, such as an environmental impact statement.
- 3. Right of First Refusal
The
new law requires that a lease of power privilege be offered first to an
irrigation district or water users association operating or receiving
water from transferred or reserved conduits. The law defines: (i)
“reserved conduit” as any conduit included in project works whose care,
operation, and maintenance has been reserved by Reclamation; and (ii)
“transferred conduit” as any conduit included in project works whose
care, operation, and maintenance has been transferred to a legally
organized water users association or irrigation district.
If the
irrigation district or water users association elects not to accept a
lease of power privilege offer, Reclamation must offer the lease of
power privilege to other parties.
Litigation Issues
The
use of a categorical NEPA exclusion under the Reclamation Act and the
expedited licensing process combined with the new exemption from license
requirements under the Hydropower Efficiency Act is expected to reduce
costs incurred by small hydropower project developers, including costs
associated with long processes and protracted litigation.
These
new streamlined processes and reduced bureaucratic and litigation costs
should help induce construction of small hydropower projects. However,
it remains possible that some environmental groups or third parties
attempting to halt construction of specific hydropower projects
challenge the implementation of these streamlined processes.
This article was largely published in the ABA Section of Environment, Energy & Natural Resources – Litigation Committee Newsletter, December 2013, Vol. 2, No. 1.